Vacuum and Epics: Difference between revisions
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
	
No edit summary  | 
				|||
| (23 intermediate revisions by the same user not shown) | |||
| Line 1: | Line 1: | ||
=Login=  | |||
*To bring up epics, ask Annika or Martin for access to isacepics login.    | *To bring up epics, ask Annika or Martin for access to isacepics login.    | ||
=Navigation=  | |||
*From the main menu, go to "vacuum2->HEBT-GP3" to open the ANASEN vacuum page (called HEBT-GP3 Vacuum)  | *From the main menu, go to "vacuum2->HEBT-GP3" to open the ANASEN vacuum page (called HEBT-GP3 Vacuum)  | ||
[[File:epicsmenu.png|600px|thumb|center|Epics menu]]  | |||
[[File:hebtgp3.png|600px|thumb|center|HEPT-GP3 vacuum page]]  | |||
*To view conditions of upstream beamline, click the "HEBT" button on the left of the page.  | *To view conditions of upstream beamline, click the "HEBT" button on the left of the page.  | ||
[File:  | [[File:hebt3vacuum.png|thumb|center|600px|HEBT3 Vacuum]]  | ||
=Pump down=  | |||
[[File:HEBT_valves.jpg|500px|thumb|center|HEBT valves position.]]  | |||
[[File:HEBT_valves2.jpg|500px|thumb|center|Manual valve - HEBT:MV19.]]  | |||
===No window (fast pump down)===  | |||
*For fast pump down, make sure the manual valve is fully open  | |||
*Close HEBT:VV19 (if open)  | |||
*Start HEBT:RP19 and observe pressure on HEBT:CG19B  | |||
*Once HEBT:CG19B is showing a reading below 50mTorr, open HEBT:PB19  | |||
*  | |||
===With window (slow pump down)===  | |||
=Venting=  | |||
==No window (slow venting procedure)==  | |||
==With window (fast venting procedure)==  | |||
Latest revision as of 01:54, 16 June 2022
Login
- To bring up epics, ask Annika or Martin for access to isacepics login.
 
- From the main menu, go to "vacuum2->HEBT-GP3" to open the ANASEN vacuum page (called HEBT-GP3 Vacuum)
 
- To view conditions of upstream beamline, click the "HEBT" button on the left of the page.
 
Pump down
No window (fast pump down)
- For fast pump down, make sure the manual valve is fully open
 - Close HEBT:VV19 (if open)
 - Start HEBT:RP19 and observe pressure on HEBT:CG19B
 - Once HEBT:CG19B is showing a reading below 50mTorr, open HEBT:PB19